Jefferson is located between Rose and Ada Streets and Acton, just a little ways below Sacramento. The school is located in the District’s northwestern elementary attendance zone. This zone does not have the capacity to house all the children. The District undertook a project to increase the capacity by two classrooms this summer, but will need to further increase the capacity in the future.
Project Manager: Mauricio Davila, Turner Construction, madavila@tcco.com
Construction Scheduled to Begin: March 2013
Proposed Completion Date: Late Spring, 2014
Architect: WLC Architect
Funding: Measure I of 2010 Facilities Bond
Budget: $5.4 M Construction Budget (Includes expansion of 4-5 classrooms and modernization)
Public Notice: Community Meeting Wednesday May 30, 2012 6:00 to 7:30 p.m. Location: Jefferson Library
Jefferson Community Frequently Asked Questions
Jefferson Community Meeting Notes – December 8 2011
Jefferson Community Meeting Notes – March 22, 2012
Jefferson Construction 03-28-2012_Timeline
On March 7, 2012 WLC Architects presented the School Board with the conceptual designs for the proposed classrooms and modernization at Jeffereson Elementary School. See the video presentation here.
Oversight:
- Site Committee forming (contact the school to become a member)
- Community Meetings December, 2011 and March 22, 2012
- Division of State Architect and the School Board