West Campus Construction 2010-12
District administrative offices have moved into their new home in the renovated West Campus building at 2020 Bonar Street at the corner of University Avenue. While the physical location has changed telephone numbers and email addresses remain the same.
The West Campus site is still undergoing the two remaining projects planned for this Berkeley Unified School District property.
West Campus Community Meeting Minutes from 10.18.11. and Project 2 GraphicNotes 10.18.11.
Project 1: West Campus Education Center
The Berkeley Unified School District renovated the classroom building ‘C’ on Bonar Street at the West Campus site to house the Central Office Administration. Parking is provided in a re-surfaced lot near the old Boys Gym around the corner on Browning Street.
Architect: Baker Vilar Architects
Construction Began: May, 2010
Proposed Completion Date: Administration moved in the first week of August, 2012
Funding: Measure AA & Measure I
Oversight:
- Site Committee
- Community Meetings Minutes 10-18-11
Project 2: West Campus School Board Room
The West Campus School Board Room will replace the Old City Hall Council Chambers for public meetings of local school officials. The Board Room will be located in the old cafeteria adjacent to the administration building on Addison Street. Possible use of this room for Berkeley City Council Meetings is still being discussed by the School District and the City of Berkeley.
Project Manager: Mauricio Davila, Turner Construction - madavila@tcco.com
Architect: Baker Vilar Architects
Construction Schedule to Begin: early 2012
Proposed Completion Date: mid-2012
Funding: Measure AA
Oversight:
- Site Committee
- Community Meetings: Community Meeting Notes 07.12.11, Minutes 10.18.11, West Campus REALM Project Graphic Notes 10.18.11
- Approvals required: School Board, Division of State Architects (DSA)
Project 3: West Campus High School Career Technical Education and Possible Charter School Program
The West Campus Career Technical Education and possible charter school project will create classrooms and support spaces for 400 students at West Campus. The school will use the existing gymnasium and several newly remodeled classrooms. They will also use the old administration building and the old shop building.
The Berkeley School Board approved a charter application for the REALM Charter School in 2010. School Districts are required to provide equivalent space for charter schools. The Berkeley School District and the REALM Charter School agreed that the middle school would be housed in commercial space and that the high school would be housed at West Campus. West Campus needs extensive renovation to safely house the school. The high school program will have no students at West Campus in 2011-12, as many as 100 students in the 2012-13 school year, as many as 300 students in the 2013-14 school year and reach its maximum capacity of 400 students in the 2014-15 school year. The District can accommodate the 100 students without extensive renovations, but must renovate additional buildings in order to house the 300 students for the 2013-2014 school year.
Project Manager: Mauricio Davila,Turner Construction - madavila@tcco.com
Construction Scheduled to Begin: March 2013
Proposed Completion Date: November 2013
Architect: Beverly Prior/HMC Architects
Funding: Measure AA
Oversight:
- Site Committee (members of the community, representatives of the Charter School, and the District’s Career Technical Education expert)
- Community Meetings: Community Meeting Notes 07.12.11
- Approvals required: Division of State Architect and the School Board
Bonar Building 3rd Floor
The 3rd floor is Special Education, Education Services and the Superintendent’s Office.
The 2nd floor is the Business Office, Human Resources, Payroll, Risk Management and Purchasing.

2nd Floor North Lobby - Waiting Room for Payroll and Risk Management/Benefits on the left and Human Resources on the left.

Human Resources - 5 Offices, 2 Conference Rooms, File Room, Interview Room and Reception directly ahead.
The first floor is still in a primary stage of construction as this was the work/staging area for all of the retrofitting work that took place under the building.